Spring is generally a dry season in Nepal; wind whips up dust along the roads, and water becomes a precious commodity. In Melamchi, the fields around the valley bottom are green with winter wheat, thanks to irrigation – but the terraces on higher slopes are mainly bare. Except, that is, where small irrigation systems exist. Many of these were damaged by the April 2015 earthquake; indeed, in some cases, even the water sources themselves were affected – some dried up, and some reappeared in other places. With funding through Swiss Solidarity, the Helvetas project Recovery of Agricultural Livelihoods (ReAL) has been working since August 2016 to reconstruct irrigation facilities. The project also supports government and private agricultural extension services, works with agricultural input suppliers in building their capacities, and rehabilitates rural water mills (for grinding grain). Social mobilisation is facilitated by the local NGO partner CDECF.

Dawa Sangbo Gurung, Jamyang Tamang, Gyalzen Lama and Pem Bahadur Gurung, pictured here, are members of the Halde Water Users Committee (WUC) – a group receiving water from an irrigation canal that has existed, they say, for at least two generations. The membership currently comprises 24 households, all of indigenous hill ethnicity (Janajatis), and all possessing land in the small settlement of Halde, mid-way up Melamchi valley. Some have only small plots – others more, but none are big landowners; the landholding size ranges from 0.1 to 0.8 ha. It is land that, without irrigation, barely supports a single crop per year; with irrigation, they can grow both paddy in the summer, and wheat or vegetables (mainly for sale) in the winter to spring season. As a result of the earthquake, the irrigation system feeding their fields was completely blocked by a landslide. Once the group members got over the immediate period of rebuilding their homes after the earthquake, renovating their irrigation system became a major preoccupation.

The WUC members first approached the local government – at the time, the Village Development Committee, VDC; under the new federal system, Halde is now part of the Helambu Rural Municipality (which has also endorsed the renovation). Although the scheme was prioritized, there was no money, so the WUC sought support from ReAL/Helvetas. District Programme Coordinator for Helvetas, Narjung Shahi, outlines what happened next.

Technical challenges

The first idea was to tunnel a pipe through the landslide area. However, a survey report showed that this was not feasible – the pipe was difficult to clamp onto the unstable mass of boulders and soil, and even had this been possible, it would have quickly become blocked by debris. We realised that the only possibility was to excavate a new channel, cutting a 5m deep and 60m long portion through the landslide area (as shown in this photo taken at the time). This was actually quite a risk – the cost of bringing in an excavator came to a substantial part of the budget, and we were not fully certain that the excavation would hold. It might simply have collapsed. However, the WUC members were very persistent, so we decided to go ahead.

Community cohesion

What has been particularly important in this renovation activity is the willingness of everyone to work together. We sat together for many meetings with the WUC and our local partner, CDECF, to discuss what to do, and how to do it. Having no alternative means of irrigation, the WUC members were ready to do whatever possible on their part. The photo at the top of this article shows the members working together on the construction.

Dawa Sangbo Gurung, the WUG Secretary, adds as follows: “We didn’t have any knowledge or experience of this type of excavation, so we brought two masons from Barabise who know about such things. They stayed with us for 169 days, and advised us on what to do. Everyone came to help – women as well as men. Although the excavator made things easier, we also had to dig out stones ourselves. In the end this took a lot of time, as we couldn’t work every day. We had other work that we had to manage as well… So whilst we started at the end of Jestha [mid-June], we only finished in early Karthik [late October]. During the latter half of the project we managed to construct part of the canal by ourselves; now the women too can prepare the cement mortar, fix the reinforcement and support construction. Everything we did, we discussed – maybe in total we had 22 or 23 meetings, and for all of them, we kept minutes.”

Water now passes along the cement-lined channel, irrigating the 12 ha of land in which crops of potatoes, tomatoes, cauliflower and wheat are flourishing. Through ReAL, the WUC members are also receiving training and support in agricultural and marketing aspects, such as through Farmer Business Schools, conducted in collaboration with the local Angrima Cooperative.

Canal maintenance

Establishing a mechanism for canal maintenance is an essential part of such renovation work. The WUC has selected two caretakers, who have received appropriate training. A water distribution system has been agreed, and an Operation and Maintenance fund established. For this, the WUC has opened a bank account; through member contributions, it currently has a balance of roughly US$ 310. They have decided to make an annual contribution of a further NRs 4,000 (roughly US$ 38) per ha, divided by household according to landholding size. As agreed with the (government) National Reconstruction Authority, ReAL/Helvetas is reconstructing 40 irrigation schemes, out of which 25 had been completed by December 2017.

«Before this work commenced, we had many worries; we couldn’t feel safe in our own home, and we doubted that it could ever be strong again.»

Bimala Dahal

“When the work began, my doubts grew. But once I became engaged myself, I became convinced. The government is giving Rs 3 lakh to those who rebuild their homes, but this is only enough for a small, single storey house. For this work [she indicates the retrofitting] we will only get Rs 1 lakh, but we will have a two and a half storey house. And it is a house that holds many memories for me; it was the house that my in-laws built, and to which I came as a bride aged 16. Now I am 51, so you see, I have lived in it most of my life…”

Bimala lives in Purano Jhagajhuli, ward 5 of Sunkoshi Gaunpalika (municipality). The retrofitting of her house is being conducted through Helvetas under the Employment Fund Reconstruction Skills project, with financial support from DFID, and in collaboration with Build Change – whose engineers are present on site along with engineers of the local partner RIMC. In theory, the concept has much to recommend it. For the government, it is cheaper in terms of compensation. For engineers, it is a technical challenge that those concerned consider to have been well mastered. For the house owner – and here Bimala’s comments echo those of others – it offers the possibility to retain a relatively large, two or two and a half storey house to which there is an emotional attachment. Government guidelines for building earthquake-resilient homes eligible for the Rs 3 lakh compensation allow only for single-storey buildings (see other blogs on this topic). A further argument in favour of retrofitting is that it preserves some of the architectural heritage of rural areas devastated by the earthquake. The traditional lime-washed or mud-washed two-storey houses have become a rare sight in such areas – replaced by squat but solid simple homes or, in the case of wealthier residents who have gone ahead with construction without government support, large concrete edifices.

There are nevertheless critics of retrofitting. The concept fits poorly with the idea of training local people in earthquake-resilient building techniques so that they can gain regular future employment as masons and carpenters. They can of course work on other retrofitting sites, but always in the presence of qualified engineers – the current norm is four engineering staff per house including two trainers. This makes retrofitting quite expensive if the whole cost is borne by the house owner, rather than subsidised by a project. Other critics point out that those families who enjoyed a two-storey house prior to the earthquake were not the poorest in their communities. This is broadly true, although they may still have suffered major losses, including the death of loved ones. Bimala’s family escaped that fate – and as her husband owns a small restaurant in which two of the couple’s sons also work, it may be surmised that they are not poor. As Brahmins, they are also socially advantaged. Yet it was they who were willing to take the perceived risk of retrofitting when others in the community held back.

Another family that was prepared to take this step is that of Bil Bahadur Bhujel. Their house is now finished, and awaiting only the final façade. Mud-washed, in keeping with local Bhujel traditions, or lime-washed as is more common amongst some others, including Brahmins? Both families want neither; they plan to paint their house in bright colours after final plastering with cement. It is of course their right to decide, but proponents of architectural heritage are likely to be disappointed with their choice.

Retrofitting will continue to have its proponents and critics. For Helvetas-Nepal, it remains a relatively niche option, worth supporting in certain cases, but not a major solution to the earthquake reconstruction effort. It is thus not planned as a part of the upcoming extension of the Employment Fund – Skills for Reconstruction project.